Frontiers Determining the Difference between Predicted vs. Actual Lighting Use in Higher Education Corridors
Frontiers Determining the Difference between Predicted vs. Actual Lighting Use in Higher Education Corridors
The occupancy in the three corridor data collection areas is shown alongside the predicted value of operational hours in Figure 5, from the three areas a median value of 831 per annum, and SD of 354 (h/annum) are calculated. The predicted annual CO2e emissions and electricity consumption are compared with the measured values using the before and after process in Table 2 and is shown in Figure 4. Operational hours are used as a proxy for occupancy hours which is in turn used as a proxy for lights on hours. The heuristics, or rules of thumb, used in the assumptions could be perceived as overoptimistic in their major underestimation of the actual patterns of lights on hours which are 138% higher than predicted operational hours. The energy efficiency predictions for electricity consumption and reduction in CO2 equivalent emissions for the three buildings are detailed in Table 2. The designs and calculations used in these projects were carried out in 2012 and 2013, since then the LENI calculation has been further refined, for differentiating daytime, night time, and parasitic consumption, nonetheless the original calculation is used for comparison purposes.
For Office 17, significant parameters are the lighting and equipment power densities, typical for office buildings that are naturally ventilated. Although, some of these parameters have a strong correlation with individual end-uses, their effect on total energy is negligible, as presented on the right side of the diagram. This was primarily helpful to capture the uncertainty of the Variable Refrigerant Flow (VRF) control strategy. The inputs and outputs were used to understand the sensitivity of the input parameters on the outputs. By varying the input parameters within the model, their individual impact on different end-uses can be analyzed. Then, the time series is again scaled to between 0 and 1, and a typical weekday and weekend day were calculated, as shown in Figure 7.
In addition, typical lighting and equipment baseloads under compliance modeling are a gross under-prediction of actual baseloads measured in the four case study buildings. In Figure 8, energy end-uses for 3,000 simulations are compared with measured energy use (orange circles), displaying the uncertainty for each end-use. The carbon savings predictions that form the basis of this performance gap assessment for corridor lighting, are calculated using Eq. The metrics for assessing the use of corridor lighting in practice against project carbon and electricity saving estimates provides insights that could also be used in other mechanical and electrical installations in buildings, not just lighting. EB is CvD’s academic supervisor during his doctoral studies and has reviewed the paper and provided feedback on the work, including direct insights from his own work. This paper highlights that a stronger emphasis on the use of performance modeling is needed, in order to drive design decisions that will effectively mitigate the risk of the energy performance gap.
The assumptions used in the calculations for estimating the operating hours of lighting after the retrofit were 2,100 (h/annum) for both Urban 2 and Urban 3. Inputting the measured lights on hours into the original calculation for the after scenario, this project has saved more annual electricity and annual CO2e emissions than originally predicted. The predicted annual CO2e and electricity consumption are compared with the measured values using the before and after process in Table 2 and is shown in Figure 8. Operational hours are used as a proxy for occupancy hours which is in turn used as a proxy for lights on hours which supports the previous building’s analysis. The predicted 8,222 annual operating hours were calculated from survey data where prior to the retrofit some of the corridor lights did not have switches and remained on constantly, some were on for up to 80% of the year.
For reporting the performance gap in percentage terms, following the convention of other performance gap researchers (Bordass et al., 2001; Menezes et al., 2012; van Dronkelaar et al., 2016), the final comparison of predictions vs. actual data are displayed in Figure 13. The heuristics, or rules of thumb, used by the external consultants in the predicted operational hours have a large variability and error compared with actual measured values. The predicted operational hours, measured lights on hours, and measured occupancy hours across all three buildings are plotted in Figure 12.
This paper quantifies the impact of underlying causes of the regulatory energy performance gap in four case study buildings. The use of the HOBO™ loggers in lighting applications enables commissioning engineers to reduce the performance gap between the lights on hours of use and occupancy patterns. Using environmental loggers can provide an additional tool to support decision making in energy efficiency projects. However, as envisaged the Urban 2 location had a higher footfall from students due to the classrooms on the second floor and was almost 800 h in addition to those predicted in the original calculations. Maths 1 has been calculated using overestimates of operating hours both before and after the upgrade. The actual patterns of lights on hours after the corridor lighting retrofit are 67% lower than predicted operational hours.
For example, boiler efficiency is weakly correlated to total energy use, because of the small percentage of gas use out of total energy use, used solely for radiator heating within circulation spaces. For each model, parametric simulations created an input- and output space (i.e., samples of input parameters and predictions of energy use). Uncertainty analysis quantifies uncertainty in the output of the model due to the a related source uncertainty in the input parameters. Differences between predicted and measured energy use were compared on a detailed level to identify performance issues. It is the process of changing input parameters in order to obtain a model that lies within agreed boundary criteria and is therefore likely to predict future options more closely related to the actual situation. Whereas, the static performance gap is not well-understood, because performance modeling has not been common practice among practitioners, and where it is undertaken, predictions are often not validated.
A higher level of data granularity and availability of evidence can filter out inaccurate predictions. Occupancy, lights, and equipment schedules for the calibrated model compared with NCM (in black) assumptions for CH. The percentage impact on total energy use for each simplification is shown in Table 4. To determine the impact of regulatory assumptions on energy use predictions and consequently the performance gap, typical NCM assumptions (i.e., simplifications) were applied to the manually calibrated base case models.
The corridor locations—which are outside of classrooms—were specifically chosen to represent corridor spaces outside classrooms which are not solely occupied by one school or department but can be centrally booked by any group booking. For the period considered, the closure dates were 24 December–3 January and over the Easter period, including Maundy Thursday through to Easter Monday. All three buildings had corridor lighting assessments from the university’s external consultants, in house project managers, and sustainability team.